Where BAI11 sits among the 40. Select any spoke to jump.

Practices9
Activities in COBIT 7106
New at level 130
AccountableChief Executive Officer, Steering (Programs/Projects) Committee

Activity load by practice and level

PracticeL1L2L3L4L5Total
BAI11.01
Maintain a standard approach for project management
22111 7
BAI11.02
Start up and initiate a project
37111 13
BAI11.03
Manage stakeholder engagement
32211 9
BAI11.04
Develop and maintain the project plan
46311 15
BAI11.05
Manage project quality
22311 9
BAI11.06
Manage project risk
43311 12
BAI11.07
Monitor and control projects
44331 15
BAI11.08
Manage project resources and work packages
47221 16
BAI11.09
Close a project or iteration
41311 10
All practices 303421129 106
Level 1, new in COBIT 7 Level 2 Level 3 Level 4 Level 5

Who owns what

Role.01.02.03.04.05.06.07.08.09
Chief Executive Officer A
Steering (Programs/Projects) Committee AAAAAAAA
Chief Information Officer RRRR
Program Manager RRR
Project Manager RRRRRRRR
Chief Risk Officer RR
Chief Technology Officer R
Business Process Owner RRR
Project Management Office RRRRR
Head Development RRR
Information Security Manager RR

R is responsible, A is accountable. One accountable role per practice.

Goals it serves

AG03 · primaryRealized benefits from I&T-enabled investments and services portfolio
AG06 · primaryAgility to turn business requirements into operational solutions
AG09 · primaryDelivering programs on time, on budget, and meeting requirements and quality standards

Secondary: AG05 Delivery of I&T services in line with business requirements